Khalifa Staduim District cooling plant control room
Instrument system design
Robust industril control system design
Khalifa Staduim DCP control work which include process design, coordination, testing and tuning, commissioning and start-up, trouble-shooting and staff training of an Integrated Control System (ICS).
Conduct a walk-through energy audit (based on ASHREA Level 1) to identify low-cost / no-cost energy conservation measures along with estimated energy savings per ECM.
Comprehensive engineering study Issue final report with findings, solutions and recommendations to resolve the low ΔT.